THE ROYAL NAVY SUBMARINE MUSEUM DEVELOPMENT PLAN

 

2002-2005

(updated April 2002)


CHAPTER ONE

THE DEVELOPMENT COMMITTEE

 

 

Introduction

 

The Museum has embarked on a programme of development to make it a fit institution in curatorial and commercial terms to justify its status as one of the six Principal Military Museums sponsored by the Ministry of Defence. To achieve an appropriate museum complex, due consideration must be given to a significant number of influences, some of which are not necessarily mutually compatible. These are:

 

·        the Museum’s product range

·        quality and quantity

·        effect and impact

·        availability of land

·        availability of finance

·        cost effectiveness

·        long term sustainability

·        relationship with neighbours

·        regard to longer term development of the area of SSI

 

Terms of Reference

 

The Committee, having taken due regard of all criteria, will:

 

·        identify the requirements

·        determine priorities

·        identify the optimum way forward to achieve the aim (ie the plan/timetable)

·        take due account of financial and environmental considerations

·        approve the design brief

·        identify appropriate contractors

·        approve final design

·        oversee the project

·        accept the project

 

Committee Membership

 

The Chairman of Trustees

Not less than two Trustees with appropriate specialist experience

The Director

The Curator

(Whenever possible the Chair of the Audit Committee will be in attendance)

 

Nominal List

 

A nominal list of committee members and observers is at Annex A.

 

 

 

 

 

 

CHAPTER TWO

THE DEVELOPMENT PLAN

 

Fundamental precept

 

No investment should be embarked upon without thought being given to its value for money and ongoing revenue consequences.

 

Investment appraisal

 

The purpose of investment appraisal is to ensure that proper consideration is made prior to making a decision to invest resources in any project. Considerations should usually include financial, and non-financial costs and benefits.

 

Financial considerations

 

      Capital costs

      Means of funding

      The financial impact of the project on running costs

      Projected operating surpluses/deficits

 

Non-financial considerations

 

      Heritage merit

      Impact on the profile and reputation of the Museum

      Non-deferrable maintenance

      Education programmes

 

The Plan

                                                                                                      -

The Museum’s development plan, itself a reflection of the remit given to it by its sponsor, The Second Sea Lord, calls for

 

(a)         the completion of the Exhibition and Interpretation of Holland 1 project.

(b)         the undertaking of the Conservation of HMS Alliance project.

(c)         the construction of the Fieldhouse Building.

(d)         the updating of Torbay Block

(e)         the development of the new Staff Room

(f)         the provision of an annex to the Cafeteria

(g)         the provision of an accessible First Aid room

(g)         the enhancement to the present Weapons Gallery

(h)         the provision of additional car parking space

(j)          the development of the Front Entrance to include

o       the provision of a Memorial Area

o       the replacement of the Weapons Gallery

o       replacement of fencing

 

Timetable

A provisional timetable for these projects is at Annex A to this chapter.

 


CHAPTER THREE

THE HOLLAND 1 PROJECT

 

Why do anything?

 

As an authoritative marketing report emphasized, in order to maintain its visitor ‘attraction’ in an increasingly competitive heritage sector, it was essential that the Museum improved its product range.

 

It was essential therefore that a project was undertaken.

 

Criteria

 

The project selected to fulfill the aim had to meet the following criteria:

 

(a)          there had to be a high degree of confidence that it would attract HLF backing (therefore have strong heritage merit)

(b)          there had to be a high degree of confidence that it would attract partnership-funding support from Industry

(c)          it had to have the potential of a high tourist profile to beat the competition and have a positive effect on visitor numbers (estimated at +20,000 by marketing survey)

(d)          it had to have a relatively short lead-time for its completion by the Royal Navy Submarine Service’s Centenary in 2001

(e)          it had to be sustainable, with overhead costs that were manageable in both the short and long terms

(f)           it had to have high accessibility potential for all categories of visitors

 

Options

 

Given the variety of constraints built into the criteria, the only viable commercial option was the Holland 1 project.

 

Additional benefits

 

In addition to meeting the basic criteria, the Holland 1 project brings with it the following ancillary benefits:

 

    it meets the Trustees’ aims and responsibilities with respect to overall care of the collection

    following its initial substantial financial support for the ‘salvation’ phase, it meets the County Council’s expectations of the artefact’s earliest possible re-exhibition

    the re-display of the Royal Navy’s first ever submarine is a most appropriate way to celebrate the Service’s centenary in 2001

    the world-wide publicity accompanying the centenary will have enormous PR benefits for the project

    it will add to the overall attraction of Portsmouth Harbour as a visitor destination

 

Summary of Project

 

The project entails converting an existing building into an environmentally controlled viewing gallery for the submarine Holland I. Additional elements in the project include conservation on the submarine, a new exhibition and the upgrading of electricity and other utilities to the Museum site.

 

Project Objectives

 

The objectives of this project are as follows:

 

      to provide the means for the long term conservation Holland I, through the provision of an environmentally controlled viewing gallery

      to substantially improve physical and intellectual access to the exhibit, through the provision of a new interpretation facility

      to improve the product range of the Museum

 

Financial summary    

 

(See end comments)

 

Financial Benefit

 

The Market Survey indicates that an additional 20,000 visitors pa can be expected. This translates into a net financial gain of £40,000 pa.

 

Additional running costs

 

      Staff. It will be necessary to man the gallery for conservation and health and safety reasons. This function will be undertaken by three part time wardens operating a similar roster to those in the Museum. The cost (£19k pa) will initially have to be borne by the Museum, although application will be made for a volume increase in GiA to cover this vital function.

      Utilities. Additional cost for utilities will be 6k pa. GiA has already been increased to cover this commitment

      Through life costs. It would be sensible to put £3k pa into a Designated Account to cover replacement costs for the dehumidification plant in 20 years time.

 

Status of matched funding

 

In place

 

THE MARKET

 

Introduction

 

Locum Destination Consulting were commissioned to undertake a market analysis to support the Holland 1 Restoration and Conservation project.

 

Locum Destination

 

The company was chosen to undertake the research because of their detailed knowledge of the broader Hampshire Tourism picture (collected as a result of their involvement in the Hampshire Museums Benchmarking Project sponsored by the County Museums Service), and their focused knowledge of the Portsmouth Harbour area (acquired through their work with Flagship Portsmouth and the Historic Dockyard).

 

Methodology

 

The methodology used is defined on Ps 5-6 of the report. It is both comprehensive and detailed.

 

Major Conclusions

 

Positive

 

    That the loss of Holland 1 from the attraction base in 1994 severely impacted on the Museum’s visitor numbers, from which it has not recovered

    That restoration of access to the submarine (both visual and physical) will reverse this trend with the potential of boosting numbers by 20,000 to ~80,000. It is of particular note that this projection has not been adjusted to reflect the likely increase in the size of the Portsmouth tourist segments as a result of the other developments in and around Portsmouth Harbour, nor does it include admissions by residents, tourists and school groups outside the 60-minute catchment. The projection of 80, 000 visitors can therefore be considered a conservative estimate.

    That the presence of Holland 1 will improve the visitor experience significantly, thereby encouraging repeat visits.

·                    That the project will contribute tangibly to the attraction of Portsmouth Harbour as a visitor destination

·                    That the Museum’s membership of the Portsmouth Harbour Consortium (marketing and ticketing), and its Waterbus jetty (access), should ensure that the Museum attracts its expected share of the anticipated boost of increased visitor numbers to the region

·                    That the launch of the Museum’s Education Initiative in January 00 will raise the Museum’s profile

    That the centenary of the Royal Navys Submarine Service, with its nation-wide publicity (newspaper and film features, Royal Mail stamp etc), will have downstream beneficial effects for its Museum

    That the Museum’s traditional visitor base (ACORN categories ABC and retired) is growing in both the 0-30 and 30-60 minute catchments as a result of business and residential development.

    The Museum is rated as good value for money by its visitors

 

Negative (but which are within the powers of the Museum to correct through its marketing campaign and future development programme)

 

    The Museum attracts few Group visits

    The Museum is viewed as ‘boys toys’

    The Museum attracts few overseas visitors

    The Museum must maintain a product renewal programme through temporary exhibitions, events and so on.

 

Completion

 

The Building was opened in May2001 by Countess Mountbatten of Burma. The project was three months late (weather and other circumstances beyond control), and it was necessary to seek additional funding of £25,000 from HLF. The quality of the building in terms of both providing environmentally stable surroundings for the historic submarine and an enhancement to the ‘visitor attraction’ was a great success.

 

The major lessons learned were:

 

 

 

 


CHAPTER FOUR

THE FIELDHOUSE BUILDING

 

 

Why do anything?

 

The recent marketing report highlights the need to

 

     maintain the visitor base in the face of growing competition

     maximize the potential of secondary income sources

     provide the visitor with a high quality visit that will generate repeat visits and ‘spread the word’

     provide modem, educational and inspirational displays for the younger visitor

     a broad product range to ‘wrap around’ the tour of HMS Alliance

 

In collection requires

 

     additional exhibition space

     higher environmental standards that presently offered by the gallery building

 

The site as a whole

 

     lacks buildings of quality

     the present admin/cafeteria building blocks out the view of HMS Alliance from Millennium Promenade

     the present building arrangements fail to exploit the asset of the waterfront outlook

 

It is essential therefore that a project is undertaken.

 

Criteria

 

The building provided must

 

(a)         enhance accessibility for all visitor groups

(b)        be energy efficient

(c)         be thematic and have landmark qualities to match other attractions around the Harbour

(d)        be of sufficient size and scope to provide the required facilities for public services and collection needs

(e)         have a positive effect on visitor numbers

(f)         exploit the waterfront must be energy efficient

(g)         must provide a high level of access for all visitor groups

(h)         should be of high quality in design and appearance to meet HLF expectations

 

Selection

 

The Development Committee selected Robert Warren (RW) as the architect.

 

Feasibility Study

 

Although relatively expensive at £30k, RW produced a quality product that covered all the essential elements for a Stage 1 HLF bid.

 

 

 

 

Costs

 

The capital cost of the project, including conservation costs of HMS X24 and the employment of an in-house monitor, will be capped at £2.4M. Assuming a 66% grant from HLF, this leaves £305k to be raised in matched funding, after other allowable partnership funding has been taken into account. It follows that any lesser offer by HLF will result in an increase in the Museum’s cash contribution.

 

Financial benefit

 

Although detailed market research has yet to be undertaken, it is estimated that the building will add 10,000 visitors per year. This will yield £20,000 additional gate income.

 

Secondary income sources (giftshop, cafeteria and corporate entertaining) should yield an additional £20,000 pa.

 

Running cost implication

 

Staff                  It is anticipated that three additional part-time wardens will be required at a cost of £20k.

 

Utilities           Annual utility running costs will be in the order of £15k. Past experience suggests that at least an element of these costs will be funded through GiA.

 

Through life costs       It would be sensible to set aside £5k pa in a Designated Fund to cover plant replacement costs.

 

Planning Permission

 

Planning permission was obtained from Gosport Borough Council in June 2001.

 

Bid Timetable

 

The Stage 1 bid was submitted to HLF in October 2001. A reply is expected in May 2002.

 

 

 

 

 

 


CHAPTER FIVE

HMS ALLIANCE

 

1            Why do anything?

 

HMS Alliance, a member of the prestigious Core Collection of Historic Ships of the United Kingdom, and the jewel in the Museum’s crown with respect to visitor attraction, has been on display since 1982. Like all metallic objects exposed to the elements, particularly sea-air, she requires constant attention, and should be the subject of a comprehensive and rigorous conservation programme. It is to be regretted that, because of other extreme pressures on the Museum’s limited budget and lack of curatorial expertise, she has not received the attention that she deserved.

   

2             Condition surveys

 

Two condition surveys conducted by Fleet Services Ltd (Portsmouth), and the

Mitie-Lindsay Group in conjunction with Babcock, came to similar conclusions.

These are:

 

     The general condition of the exterior of the submarine is poor and requires immediate work, but is well within the scope of repair rather than write-off

     The condition of the pressure hull is fundamentally sound, but requires preservation.

     The work required to the submarine is confined to external items, and comprises renovation and ‘cosmetic surgery’.

     The present condition of the submarine casing and supporting structure at the forward end is unsafe, and may become detached if remedial action is not taken.

     The reforming/repair of the bow area can be carried as a totally separate exercise to the work required on the remainder of the submarine.

     The condition of the remainder of the submarine casing is fundamentally sound, but requires some attention to the supporting structure and would benefit from the removal of (now) unnecessary under-casing pipe work and corroded supports.

     The work required to the rest of the submarine can be completed in later phases, and is not as urgent as the front-end work.

   

3             Areas of concern

 

Fore-end structure

 

The main area of concern is the bow section forward of frame 18, the free flood area. This portion of the submarine is in very poor condition as described below;

 

     External structure. Currently of steel construction this is formed of light plate, parts of which have already fallen off. Many shell plates have sprung or are holed in places.

 

           Internal structure. Currently of steel construction, the structure consists of flats (horizontal plate diaphragms), plate frames and a centreline bulkhead. The internal structure is in poor condition to the extent that some members are 100% wasted. It is likely that much of the remaining structure has diminished close to this.

 

·                    The stern contour plate is very badly corroded, and is unsightly and is one of the first areas to be viewed by visitors.

 

Stabilizers

 

The after stabilizers are in poor condition, holed and corroded severely.

 

Tank Lids

 

The tank lids collect water and are leaking, and should be replaced.

 

Shell fairing plates in way of forward hydroplanes

 

The shell fairing plates are completely wasted in the region of the forward hydroplanes.

   

4            Criteria

 

The remedial option adopted must fulfill the following criteria:

 

     It must attract HLF support

     It must be ‘non-interfering’ to the visitor operation

     For financial reasons, it must be able to be staged

     It must be sustainable under a ‘conservation plan’

   

5             Options

 

To date two options emerge that must eventually decided upon by the Development Committee

 

     A radical solution that involves removal and remodeling of the bow section in aluminium. This would be followed by a staged refurbishment/replacement of other areas of concern identified. (Mitie/Babcock) (£380,000 followed by £400,000).

     A rolling programme of repair (FSL) (£800,000)

 

6          Sources of Funding

 

HLF £500k, Partnership Funding £250k (in place)

 

7          Progress (as at Mar 2002)

 

·        the weak bow structure has been removed

·        casing plates in the vicinity of the bow and forward door have been replaced

 

in addition, for the short/medium term

 

·        there is evidence of corrosion in the lower levels that requires attention

·        the stern contour plates/after stabilizers require immediate attention

·        a scientific input will be required for the conservation plan

·        there is justification to advance the introduction of dehumidification at an early stage

 

 

Timetable

 

Having taken all the above into consideration, the proposed timetable for work appears at Annex A to this chapter.


CHAPTER SIX

TORBAY BLOCK

 

Why do anything?

 

(a)         Torbay Block houses the written and photographic archives, reserve collection, library and administrative staff.

(b)         It was falling down

(c)         It was unacceptable environmentally for a national collection

(d)         Was far from a ‘flagship’ building for a MoD Museum

 

Cost and investment appraisal

 

An overhaul of the building has merit in the following areas

 

(a)         Museum reputation

(b)         Care of the Collection

(c)         Staff working conditions

(d)         Health and safety

 

Timetable

 

The project was completed in February 2002

 

Remedial measures taken

 

MoD, at no cost to the Museum;

 

(a)         Underpinned the toilet/stores wing

(b)         Double-glazed throughout

 

(costs significant bur unknown)

 

The Museum funded

 

(a)         The creation of a classroom

(b)         The move of the Archive to the ground floor

(c)         The move of the Reserve Collection to the ground floor